Analisis Faktor yang Mempengaruhi Produktivitas Tenaga Kerja dengan Fuzzy AHP pada Proyek Bantalan Beton Divre IV Tanjungkarang
DOI:
https://doi.org/10.32832/komposit.v9i1.17563Keywords:
labor productivity factors, fuzzy analytical hierarchy process, concrete bearing replacementAbstract
Economic growth in a country can be reflected by the number of construction projects. To achieve robust economic growth, effective human resource management is required to enhance productivity. One aspect that affects work productivity is the labor force. This research aims to analyze the factors and tasks that influence labor productivity in Concrete Bearing Replacement Projects. Given the many factors or criteria to consider, the Fuzzy Analytical Hierarchy Process (Fuzzy AHP) method is used for identification. The Fuzzy AHP method assists in evaluating various criteria and determining the relative weights of each factor to make informed decisions. To simplify the analysis, 4 criteria and 12 sub-criteria are used. Based on the analysis, the factor with the greatest impact on labor productivity is the work area (K2-1) with a weight of 0.1327, while the factor with the lowest weight is the accuracy of material delivery to the location (A2) with a weight of 0.0442. The tasks that relatively impact labor productivity include loading and unloading concrete bearings (A3) with a weight of 0.0029, replacing concrete bearings with a weight value of 0.0026, and the lowest impact tasks are dismantling gongsol and revising curves, with a weight value of 0.0022.
References
Bora, P. N. (2021). Analisis Produktivitas Tenaga Kerja Pada Pelaksanaan Proyek Rehabilitasi Jalan Dan Pembangunan Jembatan Siangan-Lokasrana (Doctoral Dissertation, Universitas Mahasaraswati Denpasar). https://eprints.unmas.ac.id/id/eprint/1043
Chang, D. Y. (1996). Applications Of The Extent Analysis Method On Fuzzy AHP. European Journal Of Operational Research, 95(3), 649-655.https://doi.org/10.1016/0377-2217(95)00300-2
Edulan, E. K. (2016). Analisa Faktor-Faktor Yang Mempengaruhi Produktivitas Tenaga Kerja Tukang Batu (Studi Kasus: Hotel Grand Malebu Makasar (Doctoral dissertation, ITN malang). http://eprints.itn.ac.id/id/eprint/2128
Emrouznejad, A., & Ho, W. (2017). Fuzzy Analytic Hierarchy Process. CRC Press. https://doi.org/10.1201/9781315369884
Fajarviani, S. E. L., Usman, K., & Winarsih, A. L. C. (2022). Selection of the Use of Formwork in the Holiday Inn Bukit Randu Hotel Project Using the Fuzzy AHP Method. AVIA, 4(2). DOI: https://doi.org/10.47355/avia.v4i2.74
Faradina, M. P. (2021). Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Pembesian Dan Bekisting MTSN 3 Kota Pekanbaru (Doctoral dissertation, Universitas Islam Riau). http://repository.uir.ac.id/id/eprint/14008
Faustine, C., & Waty, M. (2022). Peringkat Faktor-Faktor Yang Mempengaruhi Produktivitas Tenaga Kerja Pada Proyek Konstruksi. JMTS: Jurnal Mitra Teknik Sipil, 681-692. https://lintar.untar.ac.id/repository/penelitian/buktipenelitian_10318005_4A270123150206.pdf
Harun, M. (2013). Analisa Produktifitas Tenaga Kerja Pada Pekerjaan Konstruksi Gedung. Jurnal Ilmiah MITSU (Media Informasi Teknik Sipil Universitas Wiraraja), 1(2). https://doi.org/10.24929/ft.v1i2.60
Mukhlisiana, M., & Adry, M. R. (2021). Analisis Faktor-Faktor Yang Mempengaruhi Produktivitas Tenaga Kerja di Indonesia. Jurnal Kajian Ekonomi dan Pembangunan, 3(3), 89. https://doi.org/10.24036/jkep.v3i3.12372
Nasron, N., & Bodroastuti, T. (2012). Faktor-Faktor Yang Mempengaruhi Produktivitas Kerja (Studi Pada Karyawan Bagian Produksi PT Mazuvo Indo). Jurnal Kajian Akuntansi dan Bisnis, 1(1), 103261. https://www.neliti.com/publications/103261/
Nofriagi, D. R. (2021). Perancangan Jalur Ganda (Double Track) Jalan Rel Ruas Kiaracondong–Cicalengka Untuk Meningkatkan Kapasitas Lintas Kereta (Doctoral Dissertation, Universitas Pendidikan Indonesia).https://repository.upi.edu/66541/4/S_TS_1604928_Chapter3.pdf
Norjana, N., & Zulfiati, R. (2020). Analisa produktivitas tenaga kerja terhadap pekerjaan kolom dan balok beton bertulang. Jurnal Talenta Sipil, 3(2), 82-86. https://doi.org/10.33087/talentasipil.v3i2.33
Nurhendi, R., & Bastam, M. N. (2023). Faktor-Faktor Yang Mempengaruhi Produktivitas Tenaga Kerja Konstruksi: Tinjauan Literatur. Jurnal Teknik Sipil, 13(1), 53-65. https://doi.org/10.36546/tekniksipil.v13i1.965
Putri, O. Y., Parabang, M., & Maulana, H. (2021). Analisa Waktu dan Biaya Berdasarkan Produktivitas Tenaga Kerja Proyek Pembangunan Jalan Penghubung Jembatan Kuranji. Journal of Applied Engineering Scienties, 4(2), 046-059. https://ojs-ft.ekasakti.org/index.php/JAES/article/view/69
Riskillah, M. I. (2014). Pengaruh Kepemimpinan, Motivasi, Lingkungan Kerja, Pendidikan Dan Latihan Terhadap Produktivitas Karyawan Pt. Adimulya Agro Lestari (Doctoral dissertation, Universitas Islam Negeri Sultan Syarif Kasim Riau). http://repository.uin-suska.ac.id/id/eprint/4187
Roesdiana, T. (2020). Analisis Kerusakan Jalan Rel Wilayah UPT Resor Jalan Rel 3.13 Tanjung Berdasarkan Hasil Kereta Ukur. Jurnal Konstruksi dan Infrastruktur: Teknik Sipil dan Perencanaan, 5(1). http://dx.doi.org/10.33603/jki.v5i1.3775
Saaty, T. L. (2008). Decision Making With The Analytic Hierarchy Process. International Journal Of Services Sciences, 1(1), 83-98. https://doi.org/10.1504/ijssci.2008.017590
Santoso, A., Rahmawati, R., & Sudarno, S. (2016). Aplikasi Fuzzy Analytical Hierarchy Process untuk Menentukan Prioritas Pelanggan Berkunjung Ke Galeri (Studi Kasus Di Secondhand Semarang). Jurnal Gaussian, 5(2), 239-248. https://doi.org/10.14710/j.gauss.5.2.239-248
Urva, G., & Aminah, S. (2022). Implementasi Metode AHP (Analytic Hierarchy Process) dalam Pemilihan Proyek Kontruksi. Jurnal Unitek, 15(2), 141-150. https://doi.org/10.52072/unitek.v15i2.405
Wirawan, W. A., Wahjono, H. B., & Rozaq, F. (2020). Desain Prototype Teknologi Automatic Surface Treatmen Untuk Meningkatkan Ketahanan Jalan Rel Kereta Api. Jurnal Perkeretaapian Indonesia (Indonesian Railway Journal), 4(1). https://doi.org/10.37367/jpi.v4i1.98
Yurizal, M. (2023). An Analysis of Factors Affecting Labor Productivity of Upper Structure Work on the Hurun Beach Resort Project Using the AHP (Analytic Hierarchy Process). Journal of Engineering and Scientific Research, 5(1). https://doi.org/10.23960/jesr.v5i1.129
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms (Penulis yang mengajukan publikasi artikel telah menyetujui hal berikut):
- Through this publication, the author agree to submit the copyright of article writing to Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil. This copyright submission takes the form of, but is not limited to: reproduction of the article and parts therein, including photographic reproductions; distribution of articles through printed and electronic documents; and translation of articles(Bahwa melalui publikasi ini, hak cipta penulisan artikel diserahkan kepada Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil. Penyerahan hak cipta ini berupa, namun tidak terbatas pada: perbanyakan artikel dan bagian di dalamnya, termasuk reproduksi fotografi; penyebarluasan artikel melalui dokumen cetak dan elektronik; serta penterjemahan artikel).
- The authors agree to the terms of the Copyright Notice, according to Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License., which will apply to this article if and when it is published by Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil. (Para penulis setuju dengan ketentuan Pemberitahuan Hak Cipta, sesuai dengan Lisensi Internasional Creative Commons Attribution-NonCommercial-ShareAlike 4.0., yang akan berlaku untuk artikel ini jika dan ketika diterbitkan oleh Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil).
This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.